Fifteen to twenty on one job
He ran residential renovations inside occupied buildings for a small general contractor in New York. Fifteen to twenty change orders on a project was normal for him.
That is far above the average. AIA Contract Documents studied 18,229 US projects and found 1.7 written change orders on projects under $500,000.
The study averages every kind of project. His were renovations in buildings people were living in.
Why renovations run high
Two reasons came up in our conversations with builders.
The client decides late. He named clients who take their time and change their minds as his biggest source of delay. Every changed mind is a change to the work.
The building has its own opinion. A superintendent on healthcare fit-outs told us about a job budgeted at about $1 million that finished at $1.3 to $1.4 million. It grew add-on by add-on because the existing building wasn't up to the client's standards.
A change gets approved three times
On his jobs a change was agreed in a meeting or on the phone. The signature came later. Sometimes it took a couple of weeks while the architect and the client got to it.
So a change is approved three times. Once in the meeting and once on the phone and once on paper.
The field doesn't wait for the paper. It builds to the conversation.
Where they get lost
The gap between the conversation and the signature is where the money goes missing. By the time the paper arrives the work is in the wall. Nobody is sure who asked or what was said about the price.
Small changes are the easiest to lose. He once gave away about $100 of insulation to keep the client and the architect happy. It is a fair call on the day. A job with fifteen changes offers that call again and again.
A builder who ran jobs in New Jersey for 38 years handled it by putting every instruction in an email. His reason was short: “So everything's on record.”
From our conversations with builders in October 2026. We credit people by role and not by name.
What to do the day it happens
You can't make the signature come faster. You can make sure the change exists in writing the day it is agreed.
- Write it down the same day. What changed and who asked and when. The price and the days can stay open.
- Send it back to the person who asked. Two lines are enough. It puts a date on the request.
- Keep the open ones in one list. A change that is agreed but unsigned should stay visible until it is signed or dropped.