What a notice deadline is
Most construction contracts make you tell the other side in writing when something happens that will cost money or time. They also say how fast. Miss the window and the contract may bar the claim however good it is.
The clock usually starts when the event happens or when you first recognize it. On site that moment is often a message in a group chat that nobody treats as the start of anything.
This guide is general information and not legal advice. Editions differ and contracts are often amended. Your signed contract decides what applies.
The periods side by side
| Contract | What starts the clock | How long you have | How it's given |
|---|---|---|---|
| AIA A201-2017 §15.1.3.1 | A claim | 21 days from the event or from first recognizing it | Certified or registered mail or a courier (§1.6.2) |
| AIA A201-2017 §3.7.4 | Concealed or unknown conditions | Before they are disturbed and within 14 days | Notice to the owner and the architect |
| VOB/B §2(6) | Work the contract didn't include | Before the work starts | Announced to the client |
| VOB/B §6(1) | A hindrance to the work | Without delay | In writing to the client |
| FIDIC 1999 cl. 20.1 | A claim for time or money | 28 days from when you became aware or should have | Notice to the engineer |
| FIDIC 2017 cl. 20.2 | A claim for time or money | 28 days for the notice and 84 days for the detailed claim | Notice to the engineer |
Summarized from the sources listed at the foot of this page. The form texts themselves are copyrighted.
AIA A201-2017
Claims: 21 days. A claim has to be started by notice within 21 days of the event or of first recognizing the condition that gives rise to it. Whichever comes later counts.
Concealed conditions: 14 days. If you uncover something that differs from the contract documents you have to give notice before the conditions are disturbed. The outer limit is 14 days from first observing them.
Delivery matters. A notice of claim has to go by certified or registered mail or by a courier with proof of delivery. An email by itself may not count.
VOB/B
Extra work: before it starts. If the client asks for work the contract doesn't include you are entitled to extra payment. You have to announce that claim to the client before you begin the work.
Hindrance: without delay. If you believe you are hindered in carrying out the work you have to report it in writing without delay. Without that notice the hindrance counts only if the client clearly knew about it and about its effect.
FIDIC 1999 and 2017
28 days. Under the 1999 forms a contractor has to give notice of a claim within 28 days of becoming aware of the event. The same limit applies from when the contractor should have become aware.
A second clock in 2017. The 2017 Red Book keeps the 28 days and adds a second time bar. The fully detailed claim is due within 84 days and without it the notice can lapse. The same procedure now applies to the employer's claims.
Check which edition your contract is built on. The clause numbers and the consequences differ.
What a notice should say
Your contract may list what a notice must contain. Where it doesn't these are the usual parts.
- What happened and where. Facts and no blame.
- The date it happened and the date you became aware of it.
- That it may affect the price or the time.
- The clause you are giving notice under.
- The person and the address your contract names for notices.
NOTICE OF [CLAIM / CONCEALED CONDITION / HINDRANCE] Project: [name and address] Contract: [form and date] To: [the person and address the contract names] Date sent: [date] On [date] at [location] the following occurred: [The facts in two or three sentences.] We first became aware of it on [date]. It may affect the contract sum and the contract time. Details will follow as they become known. This notice is given under [clause]. [Name, company and signature]
You can leave the amount open. What you can't leave open is the date.
Keeping the clock in view
- 1
Write down the date of the first mention.
The message in the group or the note from the walk. That is usually when the clock started.
- 2
Read the clause the same day.
Find the period and the delivery method in your own contract.
- 3
Put the deadline on the calendar.
Add reminders a week before and three days before and the day before.
- 4
Send it the way the contract says.
Keep the proof of delivery with the notice.
Where Talona fits
Talona starts the clock when a change or a delay is first mentioned in the chat. It takes the period from the contract you uploaded and reminds you 7, 3 and 1 day before the deadline.
It drafts the notice from the record and names the delivery method your contract asks for. A person reads it and sends it.
See the clocks running.
Every open deadline on a job in one list.