Changes nobody wrote down: a field guide to change orders

Most unpaid extra work was agreed out loud. This guide covers what to write down the day a change happens and how it gets from the chat to the bill.

Why changes go unbilled

A change rarely starts as paperwork. It starts as a sentence on site or a message in the group. “Owner wants the bigger fridge.” “Can you also move that outlet?” The work gets done because the job has to keep moving.

The paperwork comes later if it comes at all. By then nobody is sure who asked or when and the price is a guess. That is how extra work turns into free work.

Changes themselves are normal. A study by AIA Contract Documents of 18,229 US projects found an average of 1.7 written change orders on projects under $500,000 and more than 11 on projects over $50 million. They added between 3 and 5 percent to the original contract.

Those are the changes that made it to paper. The ones that didn't are in nobody's study.

Three things people call a change order

Contracts are precise about this even when sites are not. Under AIA A201-2017 there are three ways the work can change and only one of them is a change order.

What it's calledWho signs itWhat it settles
Change orderOwner, contractor and architectThe change in the work with its price and its effect on time
Construction change directiveOwner and architectThe change only. You proceed while price and time are still open
Minor changeArchitectA change with no effect on price or time. Say so before you start if you disagree

From AIA A201-2017 Article 7. Other contract forms use other names and other signatures.

A message in a chat is none of these. It is a possible change. It becomes a change order when the people your contract names have signed it.

What to write down the day it happens

You don't need a form on day one. You need six facts while everyone still remembers them.

  • What changed. The work in one sentence. “Unit 3 kitchen wall moves 2 ft east.”
  • Who asked. A name and who they work for. An owner's rep and an architect and a super each carry different authority.
  • When. The date and time it was first mentioned.
  • Where. The unit or room and the trade it lands on.
  • The evidence. The message or the voice note or the photo. A revised drawing if there is one.
  • What isn't known yet. Usually the price and the days.

Write what was said and leave out what you think it means. A record of facts holds up better than a record of opinions.

Confirm it the same day

Send a short written confirmation before the work starts. It doesn't need a price. It needs to say what you were asked to do and that the cost will follow.

Same-day confirmation
Hi [name],

Confirming what we discussed on site today, [date]:

[What was asked, in one or two sentences.]
Location: [unit or room]
Requested by: [name and company]

This is outside our current scope. We will send the cost and any effect on the schedule by [date].

Please reply to confirm.

[Your name]

Keep to facts. Leave out blame and leave out any number you haven't worked out.

Price it and get it signed

  1. 1

    Price the change.

    Labor and material and your subs' quotes. Note any effect on the schedule.

  2. 2

    Send it for a decision.

    A proposal the owner can accept or reject. Keep the confirmation and the evidence attached.

  3. 3

    Get the signatures your contract names.

    Until then the change is pending. If you're told to proceed without agreement ask for the directive in writing.

  4. 4

    Put it on the next bill.

    A signed change order that never reaches a pay application is still unpaid work.

Watch the notice clock

Many contracts take away your claim if you don't give written notice in time. Under AIA A201-2017 a claim needs notice within 21 days. A concealed condition has to be reported before it's disturbed and within 14 days.

Deadlines by contract type.

AIA A201 next to VOB/B and FIDIC.

Notice deadline guide

This guide is general information and not legal advice. Your signed contract decides what applies.

A checklist for every change

  • The change is written down the day it's mentioned.
  • It has a name and a date and a place.
  • The message or photo that started it is saved with it.
  • A confirmation went out before the work started.
  • The price and the days are stated or marked as still open.
  • The notice deadline is on the calendar.
  • It's signed by everyone the contract names.
  • It's on a bill.

Where Talona fits

Talona reads the site's group chat and your project mail. When someone mentions extra work it opens a possible change with the messages behind it and tells the lead in private.

It drafts the confirmation with the price left blank and starts the notice clock from your contract. A person reads every draft and sends it.

See how a change is caught.

From the message in the group to a change with its source.

Change orders

Sources

More to read and use.

The change was agreed out loud. Get it on paper the same day.