Fixtures take 12 weeks. That is why late changes hurt.

Stone, fixtures and millwork can take about 12 weeks to arrive. A decision made late lands on site late by the same amount.

Ignacy RuszkowskiCo-Founder & COO, Talona

Wrapped windows delivered on pallets outside a building under construction

What builders told us about lead times

We asked superintendents and project managers how long things take to arrive. These are the numbers from their own jobs.

ItemLead timeWho told us
Stone, fixtures and millworkAbout 12 weeksFormer project manager, New York
Roof trusses for a large apartment buildingSix weeks after a month's heads-upSuperintendent, 30+ years
WindowsThree weeks in a slow market and fifteen in a busy oneSuperintendent, 30+ years
TransformersNine months during COVIDSuperintendent, 30+ years

What these people saw on their own jobs. Check your own suppliers before you plan around any of it.

The transformers came with a second risk. If the site wasn't ready when they arrived they went to somebody else.

A late decision restarts the clock

Lead time is counted from the order and the order waits for the decision. Take a vanity that needs 12 weeks. If the client swaps it six weeks before the finish date the new one arrives six weeks after it.

The superintendent made the wider point. A week lost in the middle of a job adds the same time as a week lost at the end.

He also described how unevenly urgency is spread. When production slows everyone wants to know what is going on. Answers to “Hey, can you pick a color?” in his words “don't seem to be as important.”

When the change doesn't reach the field

A late change costs the most when it arrives after the work. He told us about a kitchen layout that changed late. The news never reached the field.

The windows went in exactly as drawn. Then they came out. The openings were reframed and the windows went back in.

His explanation: “Sometimes changes don't get assigned that level of urgency by the people who are not responsible for the field.”

Ordering isn't the job

Placing the order is the easy part. In his words: “Just simply ordering something offers you a pretty high failure rate if you don't follow up on it.”

He keeps a rolling log with two notes for each item. One on the day to order it. One the day before it is due to check that it is really coming.

A superintendent with 21 years in the trade told us what happens without the second note. Kitchen appliances arrived on his site with nobody scheduled to install them.

From our conversations with builders in October 2026. We credit people by role and not by name.

What to do with this

  • Put a decide-by date next to every long-lead item. Work back from the day it has to be installed.
  • Treat a late selection as a schedule change. Say what it moves on the day it is made.
  • Confirm every delivery the day before. One message is enough.

If a change moves your finish date your contract may give you a fixed number of days to say so in writing. The notice deadline guide puts the common contract forms side by side.